Project Schedule

The total contract time for the project is 18 months starting on June 1, 2020 and ending on or before November 30, 2021.

PROJECTED WORK ACTIVITY SCHEDULE

THE SCHEDULE BELOW IS SUBJECT TO CHANGE PENDING WEATHER CONDITIONS, ETC.  THE SCHEDULE WILL BE UPDATED AND REVISED ACCORDINGLY.

6/8/20 to 6/10/20 – Install 20-inch Tee and 20-inch Valve on Existing 20-inch Force Main between Brother Geenan and Novus.

Status: Complete

6/8/20 to 7/17/20 – Horizontal Directional Drill 30-inch HDPE Force Main (approx. 1,950 feet) from 4th Street to Gillespie Dog Park parking lot and Pressure Test.

Status:  Ongoing. Contractor fusing 30-inch HDPE pipe and reaming drill path to diameter needed to install 30” HDPE pipe.  Installation of the 30-inch HDPE pipe is expected to occur between 7/13/20 and 7/15/20.

6/10/20 to 9/11/20 – Install Force Main from Railroad to the WWTP and Pressure Test.

Status: Contractor has installed approximately 580 LF of pipe.

7/13/20 to 9/4/20 – Horizontal Directional Drill 30-inch HDPE Force Main (approx. 3,400 feet) from Brother Geenan to 4th Street and Pressure Test.

Status: Not Started

8/3/20 to 8/14/20 – Connect 30-inch HDPE force main to existing 24-inch Force Main piping at the Gillespie Dog Park parking lot.

Status: Not Started

9/8/20 to 9/11/20 – Connect 30-inch HDPE force main to 20-inch Valve Located between Brother Geenan & 4th Street.

Status: Not Started

9/14/20 to 9/25/20 – Connect 30-inch HDPE Force Mains at 4th Street.

Status: Not Started

9/14/20 to 9/25/20 – Horizontal Directional Drill 12-inch Water Main between Novus and Bay Street and Pressure Test.

Status: Not Started

9/28/20 to 10/30/20 – Install Water Mains between Bay Street and Novus.

Status: Not Started

11/2/20 to 12/31/20 – Slip-line Water Main between Brother Geenan and Fruitville.

Status: Not Started

1/4/21 to 3/19/21 – Slip-line Water Main between 4th Street and 10th Street.

Status: Not Started

4/5/21 to 8/31/21 – Mill and Overlay Road between Bay Street and 10th Street.

ROADWAY CLOSURE:

ROADWAY CLOSURE:

Osprey Ave. will be closed to through traffic between Fruitville and 4th Street starting on June 8, 2020 to facilitate the directional drilling of the 30-inch HDPE force main between this location and the dog park parking lot just north of 10th Street. This short segment of Osprey Ave. will be closed until about July 17, 2020.  All property owners will have access to their properties during this period.

We anticipate closing Osprey Ave. between Brother Geenan and Novus starting on July 15, 2020 to facilitate the directional drilling of the 30-inch HDPE force main from Brother Geenan to 4th Street.  This short segment of Osprey Ave. will be closed until about September 11, 2020.  All property owners will have access to their properties during this period.

.

Residents are encouraged to check this project website page for regular updates to the schedule.