Project Schedule

The total contract time for the project is 18 months starting on June 1, 2020, and ending on or before December 23, 2021.

PROJECTED WORK ACTIVITY SCHEDULE – UPDATED ON 9/24/21

THE SCHEDULE BELOW IS SUBJECT TO CHANGE PENDING WEATHER CONDITIONS, ETC.  THE SCHEDULE WILL BE UPDATED AND REVISED ACCORDINGLY.

Final connections to the new water main between 2nd Street and 10th Street are complete and Osprey Ave. between Fruitville and 8th Street has been repaved.  Please note there are a few areas (asphalt, concrete sidewalk, and curb) that will be re-worked before then end of 2021.  The segment of Osprey between 8th and 10th will be paved in March 2022 when additional pipe work is complete. 

Crews are making the initial connections to the new HDPE water main (slip-lined) between Fruitville and Brother Geenan.  The initial connections are expected to be complete by mid-October.  Crews currently are installing the “open cut” section of water main between Mound and Brother Geenan, including the initial connections.  Completion of this segment is expected by early October.  Once the new water main and initial connections are complete, the new water main and initial connections will be tested and disinfected before connecting customers (final connections) to the new pipeline.  All customers will be notified in advance of the final connections. The reuse water line will also be extended to the median along Oak during this period.   Once all connections are complete, crews will begin the restoration process including replacement of disturbed sidewalk and curb, re-paving, replacement of trees and landscaping, replacement of signage, etc.        

REMAINING WORK

7/12/21 to 10/1/21 – Contractors to make initial connections to the new HDPE water main between Fruitville & Brother Geenan. Two-way traffic will be maintained using flagmen and traffic control devices.   

Status: In progress.

9/20/21 to 10/1/21/21 – Contractor to “open cut” new water main between Mound and Brother Geenan. Two-way traffic will be maintained using flagmen and traffic control devices. 

Status: In progress.

9/20/21 to 10/1/21 – Contractor to test and disinfect new water main and initial connections between Oak and Fruitville.   Two-way traffic will be maintained using flagmen and traffic control devices. 

Status: In progress.

10/4/21 to 11/5/21 – Contractor to make final connections between Fruitville & OakAll customers to be notified prior to final connection.  Install reuse water service to median along Oak.  Two-way traffic will be maintained using flagmen and traffic control devices.

Status: Not Started

10/4/21 to 10/15/21/21 – Contractor to test and disinfect the new water main between Mound and Brother Geenan. Two-way traffic will be maintained using flagmen and traffic control devices. 

Status: In progress.

10/18/21 to 11/5/21 – Contractor to make final connections between Mound & OakAll customers to be notified prior to final connection.  Two-way traffic will be maintained using flagmen and traffic control devices.

Status: Not Started

11/8/21 to 12/17/21 – Restore/Replace all disturbed areas (concrete curb and gutter, sidewalk), medians, landscaping, etc.  Install “bulb-out” curbing at and crosswalk at Brother Geenan. Two-way traffic will be maintained using flagmen and traffic control devices.

Status: Not Started

12/6/21 to 12/10/21 – Mill and overlay Osprey Ave. between Mound and FruitvilleTwo-way traffic will be maintained using flagmen and traffic control devices.

Status: Not Started

12/20/21 to 12/23/21 – Complete punch list items and final cleanup. 

Status: Not Started

1/3/22 to 3/15/22 – Install replacement 24-inch Cocoanut force main and pave road between 10th Street and 8th Street.  Also restore and pave the Gillespie Park Dog Park parking lot. 

Status: Not Started

 

COMPLETED WORK

6/8/20 to 6/10/20 – Install 20-inch Tee and 20-inch Valve on Existing 20-inch Force Main between Brother Geenan and Novus.

Status: Complete

6/8/20 to 9/25/20 – Horizontal Directional Drill 30-inch HDPE Force Main (approx. 1,950 feet) from 4th Street to Gillespie Dog Park parking lot and Pressure Test.

Status:  Complete

6/10/20 to 9/30/20 – Install Force Main from Railroad to the WWTP and Pressure Test.

Status: Complete 

10/5/20 to 10/16/20 – Connect 30-inch HDPE force main to existing 24-inch Force Main piping at the Gillespie Dog Park parking lot.  During this period, the Dog Park parking lot will be closed, and 10th Street will be closed to through traffic between Gillespie and Goodrich for approximately 1 day.  Access to all properties in these areas will be provided.

Status: Complete

7/13/20 to 11/7/20 – Horizontal Directional Drill 30-inch HDPE Force Main (approx. 3,400 feet) from Brother Geenan to 4th Street.  During this period, Osprey Ave. will be closed to through traffic between Oak Street and Novus and from Fruitville Road to 5th Street. 4th Street will be closed to through traffic between Goodrich and Gillespie and Brother Geenan will be closed to through traffic between US301 and Osprey.  Access to all properties in these areas will be provided.

Status: The Contractor successfully completed the installation of the 30-inch HDPE pipe on 10/30/20. 

11/9/20 to 11/25/20 – Leak test the 30-inch HDPE Connect 30-inch HDPE force main to 20-inch Valve Located between Brother Geenan & Novus.  During this period, Osprey will be closed to through traffic between Oak Street and Novus.  Brother Geenan will be closed to through traffic between US301 and Osprey. Access to all properties in these areas will be provided.

Status: Complete

11/2/20 to 12/4/20 – Connect 30-inch HDPE Force Mains at 4th Street.  During this period, Osprey will be closed to through traffic between Fruitville and 5th, and 4th Street will be closed to through traffic between Goodrich and Gillespie.  Access to all properties in these areas will be provided.

Status: Complete

12/3/20 to 12/11/20 – Submit release to FDEP to place new force main into permanent operation and place force main into operation.

Status: Complete

12/7/20 to 12/11/20 – Directional drill new 12-inch HDPE water main under Mound and restore the area.

Status: Complete

12/14/20 to 12/18/20 and from 1/4/21 to 2/5/21 – Contractor to flush, clean and televise existing force main pipe in preparation for slip-lining the new 12-inch water main between Brother Geenan and 10th Street.

Status: Complete

12/19/20 to 1/3/21 – No work during this period other than flushing old force main.

1/4/21 to 2/12/21 – Install Water Mains between Bay Street and Mound.  Local traffic only will be provided.

Status: Complete

3/15/21 to 4/15/21 – Contractor to slip-line new 12-inch watermain between 2nd Street and 10th Street.

Status: Complete.

2/11/21 to 6/18/21 – Contractor to slip-line new 12-inch watermain between 2nd Street and 10th Street, connect to existing water mains and connect new services. Two-way traffic will be maintained using flagmen and traffic control devices.   

Status: Complete.

6/4/21 to 7/2/21 – Contractor to mill and overlay Osprey Ave. between Fruitville and 8th Street and between Bay St. and Mound St., including restoration of concrete curbing and sidewalks.

Status: Complete except for punch list items.